| No |
Client's And Project's Name |
Project |
Completion |
Contract Sum
RM |
| 1. |
ENERSAVE ENGINEERING SYSTEMS S/B (AzabarHoldings) |
Mechanical electrical sewage treatment
|
1992 |
60,000 |
| 2. |
ENERSAVE ENGINEERING SYSTEMS S/B (Islamic International University)
|
Mechanical electrical sewage treatment plant
|
1992 |
20,000 |
| 3. |
ENERSAVE ENGINEERING SYSTEMS S/B(Samsung Corning (M) Sdn Bhd
|
Waste water treatment plant
|
1992 |
320,000 |
| 4. |
ENERSAVE ENGINEERING SYSTEMS S/B( Chunghwa Picture Tube)
|
Sewage treatment plant |
1993 |
15,000 |
| 5. |
EBARA ENGINEERING (S) PTE LTD (Today Plastic - Prai)
|
Mechanical waste water treatment |
1993 |
700,000 |
| 6. |
EBARA ENGINEERING (S) PTE LTD (Pen Fabric - Prai)
|
Mechanical waste waste treatment plant |
1994 |
400,000 |
| 7. |
JI KIANG DIMENSI SDN BHD KUANTAN (Steel Mail)
|
Supply and install 11KV HT switchgear & 1500 KVA transformer & wiring
|
1994 |
204,616 |
| 8. |
KIN KEE STEEL SDN BHD
KUANTAN |
Supply and install 11KV HT switch gear & 1500KVA transformer & wiring
|
1994 |
541,018 |
| 9. |
GOODWAY RUBBER INDUSTRIAL SDN BHD
|
Install of 3.3KV HT motor & control wiring |
1994 |
87,046 |
| 10. |
SAM MCCOY ENGINEERING SDN BHD
|
To supply control
panel & installation
for pump system
|
1994
to
1995 |
50,000 |
| 11. |
WERTECT ELECTRICAL ENGINEERING (Goodway Rubber Industrial Sdn Bhd |
Supply & install resistance electrical control panel board
|
1994 |
90,000 |
| 12. |
WERTECT ELECTRICAL ENGINEERING (U-board
(M) Sdn Bhd) |
Supply & install electrical wiring & control panel
|
1995 |
78,000 |
| 13. |
NAITO ELECTRONIC (M) SDN BHD
|
Supply & install feeder main board & electrical |
1995 |
130,000 |
| 14. |
KIN KEE STEEL SDN BHD
KUANTAN |
Supply & install 2000 HP motor starter & capacitor bank
|
1995 |
159,000 |
| 15. |
GOODWAY RUBBER INDUSTRIAL SDN BHD |
Supply & install 200 HP & 400 HP motor
|
1995 |
55,000 |
| 16. |
SAM MCCOY ENGINEERING SDN BHD (STP Desa Anggerik Seremban) |
Supply & install electrical work for sewage plant
|
1996 |
19,000 |
| 17. |
SAM MCCOY ENGINEERING SDN BHD |
Supply & install electrical work for sewage plant
|
1996 |
48,000 |
| 18. |
SAM MCCOY ENGINEERING
SDN BHD (STP Sri Andalas Masalam Klang
|
Supply & install
electrical work for sewage plan |
1996 |
62,000 |
| 19. |
KIN KEE STEEL SDN BHD
KUANTAN |
Supply & install electrical work
|
1996 |
5,800 |
| 20. |
KIN KEE STEEL SDN BHD
KUANTAN |
Supply & install electrical work
|
1996 |
710,180 |
21. |
KIN KEE STEEL SDN BHD
KUANTAN |
Supply & install electrical work
|
1996 |
201,000 |
| 22. |
KIN KEE STEEL SDN BHD
KUANTAN |
Supply & install electrical work
|
1996 |
63,000 |
| 23. |
KIN KEE STEEL SDN BHD
KUANTAN |
Supply & install electrical work
|
1996 |
1,390 |
| 24. |
WESTIN PHILIPPINES PLAZA MANILA, PHILIPPINES |
Supply & install hotel electrical work
|
1996 |
US 1,250,000 |
25. |
KIN KEE STEEL SDN BHD KUANTAN
|
Supply & install electrical work for mill D.
|
May 1997 |
1,390,000 |
26. |
JI KANG DIMENSI SDN BHD |
Supply & install electrical work in Kuantan
|
Jun 1997 |
180,000 |
27. |
JI KANG DIMENSI SDN BHD |
Supply & install electrical work in Subang
|
Aug 1997 |
180,000 |
| 28. |
PILECON INDUSTRIAL ENGINEERING SDN BHD (Damai Laut Country Resort at Lumut, Perak) |
Supply, install, testing & commission of M&E work for sewage treatment plant
|
Mar 1997 |
97,000 |
| 29. |
CENTURY PARK HOTEL MANILA, PHILIPPINES |
Supply & install hotel electrical work
|
Mar 1997 |
US 1,100,00 |
| 30. |
KIN KEE STEEL SDN BHD (Gebeng Industrial Estate) |
Supply & install HV & MV electrical system for steel on 31.133 acre lot
|
June 1998 |
3,245,039 |
| 31. |
LIMA, PHILIPPINES |
Waste water treatment
|
Mar 1999 |
1,000,000 |
| 32. |
KINSTEEL BERHAD |
Electrical Insatllation For New Mill G
|
Sept 1999 |
1,175,000 |
| 33. |
GOODWAY RUBBER INDUSTRIAL S/B |
Electrical Installation of FASA ll for factory & Factory 3A
|
Processing |
1,128.000 |